| 2. |
On or Before 3 Months from the date of Application |
10 % |
|
| 3. |
On or Before 6 Months from the date of Appliaction |
10 % |
IDC |
| 4. |
On Commencement of foundation work / pilling work |
10 % |
|
| 5. |
On Completion of foundation work |
10 % |
|
| 6. |
On completion of the Ground floor roof slab |
9 % |
PLC |
| 7. |
On Completion of First floor roof slab |
9 % |
|
| 8. |
On Completion of Second floor roof slab |
9 % |
|
| 9. |
On Completion of sanitary piping and electrical conduits |
|
|
| 10. |
On Completion of plaster flooring |
|
|
| 11. |
On offer of possession |
|
Social Club Membership + Maintenance advance + IFMD |
| Note : Installments under sr no. 4 - 11 may run concurrently with those under s.no. 1 - 3 based on the physical progress of work at site. The demand letter for installments at S no. 4 - 11 shall be sent in advance providing for payment period of upto 15 days. |
| 2. |
On or before 1 month from date of application |
55 % |
IDC + PLC + ESSC |
| 3. |
On laying of Ground floor roof slab |
20 % |
|
| 4. |
On laying of 2 nd floor roof slab |
10 % |
|
| 5. |
On offer of possession |
5 % |
Social Club Membership + Maintenance advance + IFMD |